Southern Power Distribution Company of Telangana Limited
FlatAT&C losses, FY16 → FY23
12.9%
Latest
Telangana is drawing 11,003 MW of electricity at the current hour (2026-06-18T09:00:00+05:30 IST), per the India Energy Atlas state-page-live snapshot.
The most recent in-state generation stack for Telangana is dominated by coal at 80.1% of the metered mix. Grid carbon intensity is 950 gCO2/kWh.
Demand for Telangana is sourced from a live SLDC scrape (metered, no disaggregation needed).
Composed at 2026-06-18T09:00:00+05:30
Latest peak
11,108 MW
2-yr peak
18,548 MW
2-yr average
—
Most recent: 2026-06-15
Weather sensitivity
No nightly snapshot available yet for this state. Endpoint may not be deployed; see IEA-1023.
Slope
—
R²
—
Confidence
—
Demand's sensitivity to temperature (MW per degree) is what turns a heatwave forecast into a load forecast. A high, tight slope means cooling load dominates and peaks are weather-driven and forecastable; a weak or noisy slope means the swing factor is something else — industrial shifts, agriculture, or a data gap worth questioning.
No daily MAPE rows yet for Telangana — the nightly writer fills this once the next IST midnight passes.
| 00 | 01 | 02 | 03 | 04 | 05 | 06 | 07 | 08 | 09 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Mon | ||||||||||||||||||||||||
| Tue | ||||||||||||||||||||||||
| Wed | ||||||||||||||||||||||||
| Thu | ||||||||||||||||||||||||
| Fri | ||||||||||||||||||||||||
| Sat | ||||||||||||||||||||||||
| Sun |
Policy & RE Transition
Renewable Purchase Obligation: MNRE target trajectory vs SERC-reported actual compliance.
Latest actual
FY23 · modelled
Shortfall
vs FY23 target
A Renewable Purchase Obligation is statutory, not aspirational: a state utility must source a set share of its energy from renewables or pay a penalty. A widening shortfall against the MNRE trajectory is an early signal of either a procurement gap or a banked-REC scramble at year-end — both move power and REC prices.
No capture-rate rows for Telangana yet — the nightly writer fills this once the IEX area-clearing prices and SLDC actuals are both present for the previous IST day.
Grid cleanliness
Each cell is one hour's grid carbon intensity. Greener = cleaner, browner = more fossil — the green hours are when discretionary load is cheapest on emissions.
SOURCE: CEA carbon factors · UPDATED 10:00 IST
Generation mix
Each band is a fuel's share of generation each hour — watch the solar wedge swell midday and coal hold the baseload, independent of total load.
SOURCE: SLDC fuel mix · UPDATED 08:30 IST
Reliability — POSOCO PSP
All-time state peak
2026-03-27
Days with shortage
Within window
Cumulative shortage
Energy not served
Worst single day
No shortage in window
Adequacy calendar
Energy shortage by day
Each square is one day. Color intensity = energy shortage (MU).
Loading 90-day adequacy strip
Coverage: frequency since 2025-09-19; congestion since 2026-05-22; demand records since 2018-01-01; news since 2026-05-22.
No congestion or severe events in this window.
An hourly residential cost curve isn't published for Telangana yet — it appears once the underlying tariff data is available.
Upstream: atlas-discom-disaggregation · /v1/discom-disaggregation/hourly-residential-demand
Residential Tariff
| Slab | ₹/kWh |
|---|---|
| 0–50 kWh | ₹1.95 |
| 51–100 kWh | ₹3.10 |
10-Year Tariff History
Residential · 1 order
DISCOM Health
Aggregate Technical & Commercial losses per distribution utility, with multi-year trend.
Southern Power Distribution Company of Telangana Limited
FlatAT&C losses, FY16 → FY23
12.9%
Latest
Aggregate Technical & Commercial losses per PFC's Annual Integrated Rating of State Power Distribution Utilities. Backfilled FY16 onwards where published. Latest published edition is the 13th Rating (FY22-23 data); forward-year cells marked is_modeled=true.
AT&C (Aggregate Technical & Commercial) loss is the single clearest read on a distribution utility's solvency. Every percentage point is power delivered but never billed or collected; a worsening trend tells you a DISCOM is heading toward the payment delays that ripple back to gencos and IPPs.
INSIGHTS
Amara Raja Energy & Mobility (ARE&M) has flagged growing challenges in accessing Chinese battery technology, saying restrictions on technology transfers from China are affecting licensing arrangements across the industry and forcing Indian manufacturers to accelerate indigenous…
Syndicated from Saur Energy International · Open original →

Bondada Engineering Ltd has secured a ₹1,338-crore engineering, procurement and construction (EPC) contract from NTPC Renewable Energy Ltd (NTPC REL) for a 250 MW solar photovoltaic project integrated with a 50 MW/200 MWh battery energy storage system (BESS) in Uttar Pradesh.…
Syndicated from Saur Energy International · Open original →

Telangana Renewable Energy Development Corporation (TGREDCO) has invited bids to install 46.705 MW of grid-connected rooftop solar systems across 9,937 government schools in the state.The project will be implemented under the capital expenditure model.The scope of work includes…
Syndicated from Mercom India · Open original →
The National Institute of Solar Energy (NISE) has identified more than 102 GWp of floating solar potential across India, highlighting a significant opportunity to expand renewable energy deployment on the country's water bodies. The latest report was released by Union Minister…
Syndicated from Saur Energy International · Open original →

Hyderabad-based Trex Energy has launched REX, a 125 kW/261 kWh fully integrated, single-cabinet battery energy storage system (BESS) for commercial and industrial (C&I) applications. The system combines liquid cooling, an energy management system (EMS), and integrated AC/DC…
Syndicated from PV Magazine India · Open original →
The Telangana Electricity Regulatory Commission (TGERC) has allowed distribution companies (DISCOMs) to levy fuel cost adjustment (FCA) charges of up to ₹0.30 (~$0.003)/kWh on consumers without the Commission’s prior approval.The revised rules allow FCA charges above ₹0.30…
Syndicated from Mercom India · Open original →
The PM Surya Ghar Muft Bijli Yojana has crossed 40 lakh beneficiary households within two years of its launch, with the government now targeting 75 lakh rooftop solar installations by December 2026, Union Minister for New and Renewable Energy Pralhad Joshi said at an MNRE event…
Syndicated from Saur Energy International · Open original →

Job Description Job Purpose: The role is to be single point responsible and accountable for Sales and Business Development in the Andhra Pradesh, Telangana regions. Description of the roles and responsibilities Single point accountable and responsibility for Business…
Syndicated from Saur Energy International · Open original →

The Telangana Electricity Regulatory Commission (TGERC) has issued the Electricity Supply Code Third Amendment Regulation, 2026, requiring distribution companies (DISCOMs) to pay 18% interest per annum on excess amounts outstanding due to incorrect billing.
Syndicated from Mercom India · Open original →
After April's fireworks — a near-22% jump that left the SaurEnergy Green Energy Index miles ahead of the NIFTY 50 — May was always going to feel like the morning after. What May actually delivered was something more interesting: a month where the broad market began to wobble,…
Syndicated from Saur Energy International · Open original →

Grid reliability
Each cell is a day's unmet peak demand (POSOCO). Green = fully met; redder = larger shortfall — occasional stress days stand out against the reliable run.
Peak demand fully met every day
SOURCE: Grid-India PSP (daily) · UPDATED 16 Jun